Projects / Hines La Jolla Commons I & II

Phase I: The Hines La Jolla Commons parking structure was built concurrently with the construction of a 13-story office building constructed by Whiting-Turner. The parking structure is an eight-level (one below grade), 1,497 stall, 471,847 square foot design-build project featuring long-span beams with post-tensioned, cast-in-place construction. It is also outfitted with GEN2 glass-backed elevators, fabric facade, roof fabric structure, and parking controls. The scope of work included design, engineering, and construction of a storage office.

Phase II: An eight level parking garage in the La Jolla Village/UTC area of San Diego that is 157,000 square feet and built in conjunction with the new office tower. The new parking facility is a 483 parking stall expansion of the existing parking facility and is to be LEED certified.


 